01-05-2016


KOMISJA NADZORU FINANSOWEGO
Raport bieżący nr 68 / 2016
Data sporzÄ…dzenia: 2016-05-01
Skrócona nazwa emitenta
E-STAR ALTERNATIV ENERGIASZOLGALTATO NYRT.
Temat
Announcement
Podstawa prawna
Treść raportu:
1. ENEFI Energy Efficiency Plc _“Company" hereby informs its honourable Investors, that
significant _EUR 2-3 million_ non-planned depreciation is expected in its annual report of
2015 in relation with its project in Gheorgheni in its consolidated report through the IFRIC 12
calculation. Since under the IAS rules the intangible assets model must be followed in case of
the project in Gheorgheni, the write-off will affect the intangible assets at the consolidated
level _IFRS does not require the presentation of the investment under a concession
agreement in the project in Gheorgheni and in similar projects as tangible assets but as
intangible assets in the consolidated report, which in certain cases may be misleading for
less expert persons, therefore the Company hereby calls particular attention of its
Honourable Investors to this_.
The description implemented through IFRIC 12 is expected to have a negative effect on the
individual report of ENEFI Energy Efficiency Plc through the depreciation of the loans
provided to its affiliated company in Gheorgeni, therefore the Company is not expected to
pay dividend for business year 2015.
The Company hereby calls the attention of its Honourable Investors that the Company does
not have an audited consolidated report at the moment, therefore the above may
exclusively be assessed as the forecast of the management, which may change with respect
to the final report.
2. The Company hereby also informs its Honourable Investors that on the basis of the
information of the operations in Gheorgheni, the tribunal mad a favourable decision for EStar
CDR in the lawsuit filed by the Town of Gheorgheni _the subject of which was the
request to determine that the Town Council had voted for the modification of the price of
district heating, therefore the termination by the affiliated company of the Company in
Gheorgheni _E-Star CDR_ was unlawful, which shall be made void_.
The tribunal accepted the objection raised by E-Star CDR and rejected the action filed by the
Town to determine the approval of the draft decision of the Town Council on the price of
district heating together with the other subsequently submitted actions. The decision is not
final.

Kursy walut 2024-02-29

+ więcej

www.Autodoc.pl

Produkty finansowe na skróty:

Konta: Konta osobiste Konta młodzieżowe Konta firmowe Konta walutowe
Kredyty: Kredyty gotówkowe Kredyty mieszkaniowe Kredyty z dopłatą Kredyty dla firm